CRJV on behalf of TII are carrying out transverse duct crossing works on the N4 between Junction 14 and Junction 17, close to Mullingar.
The works began on Monday 31st May 2021 and will last for a period of 4 weeks. In order to carry out the works safely, there will be a number of closures required, reduced temporary speed limits and short diversions put in place.
The majority of diversions are up and overs at junctions, closing the section of the N4 between an off and on slip at a junction, so traffic is diverted up the off slip and back down the on slip.
CRJV have advised that works on the N4 Crossings are continuing ahead of schedule, and CRJV expect to complete the day works on Wednesday 16th June, with the night works being completed by the morning of Thursday 24th June.
A summary of the remaining 2-week program is provided below:
START DATE | END DATE | START TIME | END TIME | DURATION TIME | ROAD | DIRECTION | LOCATION | Type of TM (2) | ADDITIONAL TM DETAILS |
---|---|---|---|---|---|---|---|---|---|
14/06/2021 | 14/06/2021 | 06:00 | 19:00 | 1 day | M4/N4 | West | MP66/7 - Site 9 WB | Lane 1 Closure | Lane 1 WB closed on the approach to Junction 15, 60kph speed limit in place |
15/06/2021 | 15/06/2021 | 06:00 | 19:00 | 1 day | M4/N4 | Both | MP66/7 - Site 9 WB & EB | Partial HS Running | Partial HS Running WB & Partial HS Running EB on approaches to J15 + EB J15 On Slip Closure with Diversion WB to J16 and back to N4 EB (60kph speed limit in both directions) |
16/06/2021 | 16/06/2021 | 06:00 | 19:00 | 1 day | M4/N4 | East | MP66/7 - Site 9 EB | Lane 1 Closure | Lane 1 EB closed on the approach to Junction 15, 60kph speed limit in place |
17/06/2021 | 18/06/2021 | 19:00 | 06:00 | 1 night | M4/N4 | West | J17 - Site 1 WB | Full Closure | Up & Over at Junction 17 WB with lane 1 closed and Convoy Working |
21/06/2021 | 22/06/2021 | 19:00 | 06:00 | 1 night | M4/N4 | Both | J17 - Site 1 WB | Full Closure | Up & Over at Junction 17 WB with lane 2 closed and Convoy Working + Partial HS Running EB (with the possibility of convoy working if barrier unavailable) |
22/06/2021 | 23/06/2021 | 19:00 | 06:00 | 1 night | M4/N4 | East | J17 - Site 1 EB | Lane 1 Closure | Partial Hatched Median Running EB on approach to Junction 17 |
Content Last Updated/Reviewed: 10/06/2021