Project Programme

Contract No. 1, upgrading the existing Clonmore Treatment Plant, is scheduled for completion in the second quarter of 2010. This work will not result in inconvenience to the Public.

Contract No. 2, constructing the Interceptor Sewer and local collection sewers, will involve work in the Town itself. The programme of works is as follows:

Third Quarter 2008

  • Town Park
  • Lynn Road

Last Quarter 2008

  • Lynn Road
  • Bleach Yard
  • Sundays Well Road
  • Town Park
  • Pearse Street
  • Austin Friars Street
  • SuperValue Car Park
  • Royal Canal advance work

First Quarter 2009

  • Lynn Road
  • Clonmore Road Crossing
  • SuperValue Car Park
  • Royal Canal crossing (tunnel)

Second Quarter 2009

  • Town Park reinstatement
  • Clonmore Road to Bleach Yard including Railway crossing (tunnel)
  • Canal crossing
  • SuperValue Car Park, Austin Friar's St, Pearse St (tunnel)
  • Robinstown section

Third Quarter 2009

  • SuperValue Car Park, Austin Friar's St, Pearse St (tunnel)
  • Canal reinstatement
  • Robinstown section

Second Quarter 2010

  • Completion of Project and reinstatement work